Quantum VS Help: Sales Desk

Previous  Next  

Using Sales Order Date Fields To Measure Delivery Performance: Examples

Sales Orders have Required Date and Target Date fields (if enabled) in the Sales Order header and on individual lines. See Sales Order Date Fields And Delivery Performance for definitions.

 

The Required Date and Target Date fields can be updated as an order progresses - as described in Amending Sales Order Date Fields - and subsequently compared using an application such as Quantum VS myViewpoint to assess how well you met your fulfilment/delivery targets.

 

The following examples show common scenarios of when, how and why the Required Date and/or Target Date might be updated as the order progresses.

 

Example 1: When You Cannot Meet Your Delivery Target For The Whole Order

The Required Date and Target Date can be used to compare and update order delivery dates with those which were originally agreed with the customer. This example shows how dates can be amended when you cannot meet your original delivery target.

 

1.      On January 1 a Sales Order is raised for the customer 'Abbey Forest Products', who is ordering 3 Products: Product X, Product Y and Product Z. Sales Order dates default as follows:

 

2.      At this stage the system has assumed you can meet your default delivery time of 3 days after placing the order. However, imagine that 2 days later you realise you cannot meet this, perhaps because of delays in obtaining stock, or because of problems with your delivery lorries.

 

Therefore, on January 3 you ring the customer to explain that the earliest you can deliver is on January 8 - 4 days later than expected. In theory the customer might wish to cancel at this point, but imagine they accept the new 'expected' delivery date.

 

Therefore you retrieve the Sales Order and:

 

In this scenario, assuming you subsequently made the delivery on January 8, analysis would show that you missed the agreed target delivery date by 4 days.

 

Example 2: When The Customer Wishes To Delay The Order

This is a variation on Example 1 showing how the Required Date and Target Date can be amended when the customer delays the order.

 

1.      The Sales Order is raised on January 1 as in Example 1, whereby you initially expect delivery to be on Jan 4.

 

2.      On January 3 the customer rings and asks you to delay delivery until January 12. Therefore you retrieve the Sales Order and:

 

In this scenario, assuming you subsequently made the delivery on January 12, analysis would show that you met the agreed target delivery date.

 

Example 3: When You Cannot Meet Your Delivery Target For An Individual Order Line

This is a variation on Example 1 in which order lines are assigned different Required and Target dates.

 

1.      The Sales Order is raised on January 1 as in Example 1, whereby you initially expect delivery to be on Jan 4.

 

2.      At this stage the system has assumed you can meet your default delivery time of 3 days after placing the order. However, imagine that 2 days later you realise that although you can meet this for Products X and Y, you cannot deliver Product Z until 2 weeks later because of delays in obtaining stock.

 

Therefore, on January 3 you ring the customer to explain that you can deliver Products X and Y on January 4 as expected. However, the earliest you can deliver Product Z is on January 18 - 2 weeks later than expected.

 

In theory the customer might wish to cancel at this point, but imagine they accept the new 'expected' delivery date for Product Z. Therefore you retrieve the Sales Order and:

 

In this scenario, assuming you subsequently made the delivery on January 4 for Product X and Y and January 18 for Product Z, analysis would show that you met the agreed target delivery date for Products X and Y but missed the agreed target delivery date for Product Z by 14 days.

 

NEXT: Forward Orders